∗ Capacity: 2*3000 m3/day
∗ Location: Middle East
∗ Key Project Features:
000♦ Concept & Basic & Detail Design
000♦ Procurement Engineering
000♦ Equipment Supply
000♦ Installation Supervision
000♦ RO Skid Installation
∗ Contractor: MGET
∗ Commencement: 2021
∗ Status: completed
Project description:
3000 m3/day permeate water with feed water in TDS range of 35000-42300 ppm is produced.
The raw sea water to be supplied from Persian Gulf Sea, and after pretreatment is pumped to RO/ re-mineralization system.
Water Treatment Plant consists of following main process equipment:
000♦ Well water pumps
000♦ Dual Media filters and backwash system
000♦ Raw water storage
000♦ RO feed pumps
000♦ Cartridge filters
000♦ High pressure pumps
000♦ RO Blocks
000♦ Dosing Packages
000♦ CIP & Flushing package